Maximum nights out per week

This constraint lets you specify the maximum number of nights a resource can be away from the base per week.

Format: Number

Note: This constraint depends on the worked days setting and is incompatible with the following:

  • First stop at depot

  • Last stop at depot

  • Briefing duration

  • Debriefing duration

  • Start at first visit

  • End at last visit

Example: If a resource can stay away from the base for a maximum of 3 nights per week, set the value to 3. The system will then ensure that the resource does not exceed three nights away during the week.